Technical data
Project description
- Single-track railway tunnel with widening area to divide the line into 2 tracks
- 14 trough blocks
- 13 tunnel blocks
- Total length: 353 m
Construction method
- Cut-and-cover method
- Construction in sections in 29 construction phases
- Crossing of 9 railway tracks while maintaining railway operations, plus installation of auxiliary bridges in the tracks
- Sequence of construction of the tunnel blocks: Floor slab, concreting ceiling on shoring 2.5m below the target position under the auxiliary bridges, lifting the ceilings to the target position using 6 presses, pressure concreting the walls
Geology
- Sand, gravel
General data
Project
Neu-Isenburg intersection
Client
RTW Planungsgesellschaft mbH
Contractor
Wayss & Freytag Ingenieurbau AG
Construction period
September 2022 to September 2026
Faster from A to B
A 353 metre long, single-track railway tunnel is being built, which will pass under the existing railway tracks in Neu-Isenburg as part of the new Regional Tangent West (RTW) rail link.
As part of the RTW, the project improves regional connections and makes a significant contribution to strengthening local public transport in the Rhine-Main region. The RTW is a particular advantage for travellers and commuters in the heavily frequented Rhine-Main region.
Further projects
Frankfurt am Main
13,000 journeys shifted from car to rail every day

Wewelsfleth
Wind energy from northern to southern Germany

Neu-Isenburg
Crossing structure under nine existing tracks