Technical data
Project description
Gross floor area: 3,233 m²
Gross cubic capacity: 23,624 m³ uR
Building area: approx. 1,875 m² + approx. 625 m² = approx. 2,500 m²
Concrete: approx. 2,100 m³
Prefabricated parts: approx. 600 m²
Semi-finished parts: approx. 1,200 m² cavity walls
Reinforcement: approx. 150 tonnes
Formwork: approx. 7,900 m²
Facades: approx. 1,200 m² sheet metal facades
Roof: approx. 1,200 m² flat roof
Exterior surfaces: approx. 5,750 m²
Car parking spaces: 103
Bicycle parking spaces: 26
General data
Project
Projecthouse SUMIDA
Client
SUMIDA AG
Contractor
Wayss & Freytag Ingenieurbau AG, Passau branch office
Project planning
WÖRLEN + Partner, ARCHITEKTEN GBR
Construction time
June 2016 to August 2018
New construction of a production facility
New construction of a production facility with office and laboratory area as well as outdoor facilities.
The building consists of an approx. 1,500 m² production hall with adjoining social rooms and a two-storey office wing with an area of approx. 625 m². The construction consists of a reinforced concrete structure, largely made of prefabricated and semi-prefabricated parts (prestressed concrete trusses approx. 26 m long, reinforced concrete columns approx. 11 m high, prestressed concrete ceilings) and a flat roof with sheet metal façades. The interior is largely constructed in exposed concrete. The outdoor facilities consist of 103 car parking spaces and 26 bicycle parking spaces in addition to driveways and green areas.
Further projects
München
Shell construction with a basement and four storeys

Baumholder
Refurbishment of seven residential buildings

Baumholder
New construction of a total of 70 residential units