Technical specifications

Scope of works:

Construction of a storage sewer tunnel

  • Length: 654 m
  • Internal diameter: 3.85 m
  • External diameter: 4.50 m
  • Min. radius: 0.0 m
  • Min. cover: 3.00 m
  • Max. cover: 6.80 m

Jacking Pipes:

  • Type: DN 3850 concrete
  • Number: 218 pieces
  • Length: 3.00 m
  • Thikness: 0.35 m

Construction method:

  • Pipe jacking using an EPB shield

Geology:

  • Boulder clay, medium sand

General data

Project
Mauerpark Storage Sewer, Berlin, Germany

Client
Berliner Wasserbetriebe (BWB)

Contractor
Wayss& Freytag Ingenieurbau AG
as technical leader of a joint venture

Construction period
2017 to 2019

Net construction costs
€ 12 million

Utilisation
Water/Sewerage
Type
Storage sewer tunnel
Length
654 m
Construction Method
Pipe Jacking using - EPB shield

More Information:

As part of the rehabilitation program for Berlin's combined sewer system, the Mauerpark storage sewer was built in the Prenzlauer Berg district of Berlin, the program's largest single project to date. It has a capacity of 7,400 m³ and is intended to help stop further pollution of water bodies such as the Panke and Spree rivers.

During heavy rains, the city's sewers and sewage treatment plants often reach their limits, allowing water from the streets to enter Berlin's waterways unfiltered. This happens about 50 times a year. The purpose of the storage sewer is to absorb the amount of dirty water that the sewage system cannot hold. When the rain stops, the water is returned to the sewer system and pumped to the treatment plant for purification.

In order to minimize the impact on Mauerpark, a popular local recreation area, the 654 m long reservoir sewer was constructed using the pipe jacking method with a tunnel boring machine with earth pressure support.

The excavation began in the 11 m deep starting excavation pit in Bernauer Strasse and ran at a gradient under the paved Schwedterstrasse in Mauerpark to the target excavation pit in Gleimstrasse.

These two excavation pits were also used to connect the new storage sewer to the existing sewer system and an emptying pumping station.

The contract also included the construction of the start and target shafts as sheet pile walls and 19 intermediate shafts as access, ventilation and cleaning shafts.

A particular challenge arose due to the location of the construction site in an inner-city park, which meant that only a tightly dimensioned installation area was available. Considerable restrictions also had to be taken into account in the delivery of the jacking pipes with an outside diameter of 4,500 mm and an individual weight of approx. 32 tons.

Related Projects

Related Projects

Weser crossing
Weser crossing
Germany

1 four-lane motorway tunnel, total tunnel length 1,100 m, length of total section on our behalf approx. 4,800m.

Read more
Mine Water Drainage Tunnel, Ibbenbüren
Mine Water Drainage Tunnel, Ibbenbüren
Germany

Length: approx. 7,400 m 2 drives: West 3,230 m and East 3,8700 m in length Internal diameter: 3.60 m External diameter: 4,50 m bore diameter approx. 4.80 m

Read more
ElbX Elbe Crossing Structure - tunnel driving
ElbX Elbe Crossing Structure - tunnel driving
Germany

Due to swelling events and the associated heave and damage to the tunnel inner lining, it was planned to install protective netting in the area of the tunnel roof and the upper side walls.

Read more