Technical specifications

Scope of works:

Construction of a storage sewer tunnel

  • Length: 654 m
  • Internal diameter: 3.85 m
  • External diameter: 4.50 m
  • Min. radius: 0.0 m
  • Min. cover: 3.00 m
  • Max. cover: 6.80 m

Jacking Pipes:

  • Type: DN 3850 concrete
  • Number: 218 pieces
  • Length: 3.00 m
  • Thikness: 0.35 m

Construction method:

  • Pipe jacking using an EPB shield

Geology:

  • Boulder clay, medium sand

General data

Project
Mauerpark Storage Sewer, Berlin, Germany

Client
Berliner Wasserbetriebe (BWB)

Contractor
Wayss& Freytag Ingenieurbau AG
as technical leader of a joint venture

Construction period
2017 to 2019

Net construction costs
€ 12 million

Utilisation
Water/Sewerage
Type
Storage sewer tunnel
Length
654 m
Construction Method
Pipe Jacking using - EPB shield

More Information:

As part of the rehabilitation program for Berlin's combined sewer system, the Mauerpark storage sewer was built in the Prenzlauer Berg district of Berlin, the program's largest single project to date. It has a capacity of 7,400 m³ and is intended to help stop further pollution of water bodies such as the Panke and Spree rivers.

During heavy rains, the city's sewers and sewage treatment plants often reach their limits, allowing water from the streets to enter Berlin's waterways unfiltered. This happens about 50 times a year. The purpose of the storage sewer is to absorb the amount of dirty water that the sewage system cannot hold. When the rain stops, the water is returned to the sewer system and pumped to the treatment plant for purification.

In order to minimize the impact on Mauerpark, a popular local recreation area, the 654 m long reservoir sewer was constructed using the pipe jacking method with a tunnel boring machine with earth pressure support.

The excavation began in the 11 m deep starting excavation pit in Bernauer Strasse and ran at a gradient under the paved Schwedterstrasse in Mauerpark to the target excavation pit in Gleimstrasse.

These two excavation pits were also used to connect the new storage sewer to the existing sewer system and an emptying pumping station.

The contract also included the construction of the start and target shafts as sheet pile walls and 19 intermediate shafts as access, ventilation and cleaning shafts.

A particular challenge arose due to the location of the construction site in an inner-city park, which meant that only a tightly dimensioned installation area was available. Considerable restrictions also had to be taken into account in the delivery of the jacking pipes with an outside diameter of 4,500 mm and an individual weight of approx. 32 tons.

Related Projects
Pipe Jacking under Leipzig Main Station
Pipe Jacking under Leipzig Main Station
Germany

During the construction of the Leipzig City Tunnel in the shopping centre under the station concourse of Leipzig Main station it was not possible to carry out any works from above ground. Therefore, two pilot tunnels were driven by pipe jacking so that vertical freezing bulkheads could be built.

Read more
SMART Tunnel
SMART Tunnel
Malaysia

A clever solution: What is normally a road tunnel turns into a storm water relief tunnel during floods. The storm water management and road tunnel in Malaysia is the answer to two challenges.

Read more
Rotterdamsebaan
Rotterdamsebaan
Netherlands

2 parallel tunnel tubes with a length of 1.645 km each, inner diameter 10,15 m; 6 cross passages driven under the protection of ground freezing; 2 access ramps, which at the same time function as start and target shafts, Passing under A4/A133 motorways incl. connection to existing infrastructure

Read more