Technical specifications

Scope of works:

  • The 18 km long Fehmarnbelt Tunnel will connect the Danish island Lolland with the German island Fehmarn (SchleswigHolstein) and will be the world‘s longest immersed tunnel for road and rail.
  • It will comprise a four lane motorway and two electrified rail tracks.
  • Construction of an 18 km long immersed tunnel, construction of the tunnel factory that will produce prefabricated tunnel elements, construction of the tunnel portals, toll stations, bridges and ramps.
  • Tunnel elements: 79 individual elements, each 217 metres long, weight 73,000 tonnes, 10 special elements with a lower floor for the use of the tunnel operation and maintenance equipment.

Construction method

  • Immersed tunnel

General data

Project
Fehmarnbelt Tunnel

Client
Femern A/S

Contractor
Femern Link Contractors (FLC) with partners VINCI Construction Grands Projets, Per Aarsleff, Royal BAM Group, Wayss & Freytag Ingenieurbau AG, Solétanche-Bachy International, CFE and Max Bögl Stiftung & Co.

Construction period
2021 to 2029

 

Utilisation
Infrastructure
Type
Underwater road and railway tunnel
Length
18 km
Construction Method
immersed tunnel

Images: Femern A/S

Related Projects

Related Projects

Grand Paris Express, Linie 17, Section 1, Bonneuil-en-France
Grand Paris Express, Linie 17, Section 1, Bonneuil-en-France
Germany

New traffic connection for Paris. Europe's largest infrastructure project improves transportation networks in the greater Paris area.

Read more
Landsberger Straße Sewer System Rehabilitation, Section 2, Munich
Landsberger Straße Sewer System Rehabilitation, Section 2, Munich
Germany

A new sewerage canal through the southwest of Munich relieves the existing canal system.

Read more
Landsberger Straße Sewer System Rehabilitation, Section 2, Munich
Landsberger Straße Sewer System Rehabilitation, Section 2, Munich
Germany

Landsberger Straße Sewer System Rehabilitation, Section 2, Munich

Read more