Technical specifications

The turnkey reconstruction of the A34 truck delivery hall was realised during the user’s ongoing operations. The modernisation of the old hall comprised the reconstruction of the entire HVACR system, the partial refurbishment of the roof structure as well as the visual conversion into a new delivery hall with dimensions of 98.00 x 27.00 m.

During the reconstruction work, the new trucks continued to be delivered and handed over to the MAN customers without interruption. The fact that it was possible to hand over the delivery hall to the user on time, due to the adherence to tight schedules deserves a special mention. Wayss & Freytag Ingenieurbau AG always coordinated the processes with all parties involved.

Despite numerous unforeseen interventions by the user as well as additional works, it was possible to meet the high quality requirements and carry out the acceptance as scheduled.

General data

Client:
MAN Truck & Bus AG

Construction period:
11/2012 – 04/2013

Contract value:
approx. 825.000 €

Related Projects

Related Projects

Munich Residence
Munich Residence
Germany

New splendour for a magnificent building

Read more
Schön Clinic Munich-Harlaching
Schön Clinic Munich-Harlaching
Germany

Hospital building is extended

Read more
Northern Court of Bavarian Parliament
Northern Court of Bavarian Parliament
Germany

The extension of the Northern Court in “Passive House” standard creates a modern work environment in the Bavarian parliament, the historic Maximilianeum.

Read more