Images: DEGES
Scope of works:
Construction method
Geology
Project
Weser crossing, motorway tunnel under the river Weser
Client
DEGES
Contractor
Wayss & Freytag Ingenieurbau AG, North and Central sections
Construction period
08/2023 - 08/2028
Net construction costs
€ 650 million
Images: DEGES
A new sewerage canal through the southwest of Munich relieves the existing canal system.
Storage sewer at Berlin's Mauerpark will prevent sewer overflow into the Spree and Pranke rivers in the future.
2 parallel tunnel tubes with a length of 1.645 km each, inner diameter 10,15 m; 6 cross passages driven under the protection of ground freezing; 2 access ramps, which at the same time function as start and target shafts, Passing under A4/A133 motorways incl. connection to existing infrastructure