Technical specifications

General data

Client:
A40 Westkreuz BO JV, Heitkamp Erd- und Straßenbau GmbH / Eurovia Teerbau GmbH

Employer:
Landesbetrieb Straßenbau NRW Regionalniederlassung Ruhr

Contract value:
106,000 €

Construction period:
April 2013 - July 2013

In the course of the construction of the motorway intersection „Bochum West“, a 170 m long retaining wall was anchored back to secure the dump of the former ThyssenKrupp Nirosta GmbH site. After five suitability tests to find out the actual outer soil bearing capacity of the marl, finally 49 GEWI-tension piles with a diameter of 40 mm with double corrosion protection were installed.

The pile heads are integrated in the head beam of the bored pile wall. Particularly challenging was the adjustment of the GEWI load bearing elements to the existing marl level at site. Thus, the piles had a length of up to 17.20 m. The works, which were carried out at the construction site of the motorway intersection “Bochum West”, were completed without defects and within the agreed deadlines.

Related Projects

Related Projects

Light railway, Karlsruhe
Light railway, Karlsruhe
Germany

Anchors secure construction pit in Karlsruhe against groundwater

Read more
Ilmenau, Pile Foundations for Power Pole Foundations
Ilmenau, Pile Foundations for Power Pole Foundations
Germany

Pile Foundations for Power Pole Foundations in the Thuringian Forest

Read more
Rehabilitation of a Sheet Pile Harbour Wall in Mühlheim an der Ruhr
Rehabilitation of a Sheet Pile Harbour Wall in Mühlheim an der Ruhr
Germany

Rehabilitation of a Sheet Pile Harbour Wall in Mühlheim an der Ruhr

Read more