Technical specifications

General data

Client:
Betriebe der Stadt Mülheim an der Ruhr

Employer:
Stadt Mülheim an der Ruhr (Municipality)

Contract value:
300,000 €

Construction period:
December 2013 - February 2014

The rehabilitation of a 110 m long section of the sheet pile wall of the town harbour was carried out from the water from a pontoon with 54 injection (micro) piles type GEWI d= 50 mm with standard corrosion protection and a length of 11.50 m at a 6.0 m injection.

Only after the new walers were installed and the injection piles fixed, were the old walers dismantled, the old anchors shortened and the holes in the sheet pile wall closed.

The order further comprised the replacement of a bollard with respective foundation and six GEWI-piles to transfer the compressive and tensile forces below the harbour floor.

Related Projects

Related Projects

„Pulvermühle“ Viaduct, Luxembourg
„Pulvermühle“ Viaduct, Luxembourg
Luxembourg

Micro piles secures an embankment to a popular bicycle and footpath

Read more
Retaining wall A 40 intersection „Westkreuz Bochum”
Retaining wall A 40 intersection „Westkreuz Bochum”
Germany

GEWI-tension piles secure retaining wall

Read more
Ilmenau, Pile Foundations for Power Pole Foundations
Ilmenau, Pile Foundations for Power Pole Foundations
Germany

Pile Foundations for Power Pole Foundations in the Thuringian Forest

Read more