Technical specifications

Technical processing: Wayss & Freytag Ingenieurbau AG          

Equipment used:

  • Ram / carrier: Sennebogen HD 6100 XLR
  • Length of guide pole: 48 m
  • Vibrator: PVE 2335M / PVE 105
  • Rammer: IHC S-90
  • Work pontoon: Tarpon, 40 x 16 m

Main works:

  • Piles extracted: 420 pcs. / 1,550 t
  • Piles supplied and placed: 76 pcs. / 1,550 t
  • Steel construction Nock: 104 t

General data

Project: Remedial maintenance of the control units of the new lock of the Kiel canal in Kiel

Client: Wasser- und Schifffahrtsamt (Water and Shipping Authority) Kiel - Holtenau

Contractor: Wayss & Freytag Ingenieurbau AG Area North       

Construction period: April 2004 to October 2004

Contract value: 4.5 m €

 