Renewal of the control units during ongoing operations with own special equipment.
Technical processing / safety coordination / site coordination: Wayss & Freytag Ingenieurbau AG
Canal overpass with North and South trough: 14,800 m³ concrete, 1,832 t reinforcement, 490 m total length
Earthworks, dry / clearance /landscaping / dewatering: 850,000 m³ excavation and refill, 2.2 km total length new waterway
Dredging works with clay sealing and armour stones: 100,000 m³ dredging works, 150,000 t armour stones, 54,000 m² clay sealing, under water, 81,000 m² clay sealing, dry
Microtunnel [open channel DN 800]: 245 m length
Security works old Canal bridge [HDI / needling]: 5,000 m³ HDI, 960 needles, 2,160 m² shotcrete
Sheet piling on land /from water: 690 t on land, 600 t in water
Track construction with cable civil engineering [BUG] Emergency gates: 3,300 m³ concrete, 390 t reinforcement, 171 t steel
Demolition of old canal bridge
Project: Construction of the new HOW Havel-Oder-Waterway, [Eberswalde], Highest canal section, lot G 1, HOW-km 67.292 – 69.500, Special lots 4 to 6
Client: Wasser- und Schifffahrtsamt, (Water and Shipping Authority), Schneidemühlenweg 21, 16225 Eberswalde
Contractor: Wayss & Freytag Ingenieurbau AG, Area North, Heidenkampsweg 66, 20097 Hamburg
Construction period: 22.12.2003 to 05.02.2007
Contract value: 26.25 m €
Renewal of the control units during ongoing operations with own special equipment.