Start widescreen image

News

Brunsbüttel: Milestone reached

Yesterday, on 25 February 2021, the project team of ARGE Neubau 5. Schleusenkammer Brunsbüttel reached another milestone. Since January 2016, a total of 722 supporting piles with a total tonnage of 16,500 t have been professionally installed.

These activities resulted in the construction of four excavation pits for the subsequent construction of the reinforced concrete heads and two lock chamber walls. In addition, connections to existing structures, bank protections and jetties were built.

The highly complex work was carried out both from water and from land. Supporting piles were placed in a suspension-supported slot as well as in jacket bores. Almost 100 % of the work was carried out by the company itself.

Cookies Policy

Our website uses cookies to improve your experience. Certain cookies can contain personal information. We deactivate Cookies, unless you allow Cooky usage.
Additional information

Allow Cookies
Do not allow cookies
Cookies Settings