The project comprises the sinking of a centre shaft as a central component of the Ibbenbüren tunnel. The aim was to increase productivity in shaft sinking and to organise work processes more efficiently.
Added value
Savings of approx. 40 % of the time required
Excavator tunnelling: reduction from 7-8 days to 4-5 days → Savings: approx. 3 days per level
Pressure belt: Reduction from 8-10 days to 5-6 days → Savings: approx. 3-4 days per section