The Emscher sewer projectwas the starting point for lean construction at Wayss & Freytag Ingenieurbau AG, with the aim of making construction processes more efficient and reducing waste.
Added value
Reduction in working time per process from 17 to 8 days
58 % time saving when changing pipes (from 40 to 17 minutes)
The costs saved are estimated at around € 1,400,000 for the pipe replacement process