Technical specifications

Scope of work

Construction in two Lots
  • Lot 1: approx. 300 m South-North-Tunnel with 850 m ramp and western junction
  • Lot 2: approx. 675 m North-South-Tunnel with three ramps approx. 85 m; connection to various subterranean garages, ground levels 7 m to 14 m; 36,000 m³ concrete; 120,000 m³ excavatio

Construction method

  • Cavern with diaphragm walls or bored
  • under water concrete with rear anchoring
  • Top-Down method

General data

Project

Tunnel Kö-Bogen

Client: Landeshauptstadt (regional federal land capital of) Düsseldorf
Amt für Verkehrsmanagement (authority for traffic management)

Contractor

Wayss & Freytag Ingenieurbau AG
as technical leader of a joint venture

Construction period

2010 to 2016

Construction costs

€ 114 million
Utilisation
Infrastructure
Type
Road tunnel
Length
300 m + 675 m
Construction Method
Cavern with diaphragm walls or bored

Related Projects

Related Projects

Europagarten Tunnel
Europagarten Tunnel
Germany

60.000 m² coherent park area for approximately 40.000 inhabitants – a street tunnel makes it possible.

Read more
Europagarten Tunnel
Europagarten Tunnel
Germany

60.000 m² coherent park area for approximately 40.000 inhabitants – a street tunnel makes it possible.

Read more
Luise-Kiesselbach-Platz
Luise-Kiesselbach-Platz
Germany

The 2,800 m long, inner-city tunnel using both bored pile-cover construction method and open construction method relieves a central traffic junction in Munich.

Read more