Technical specifications

Scope of work

  • Tunnel for a gas pipeline
  • Length: approx. 4,050 m
  • Internal diameter: 3.0 m
  • start and target shaft
  • installation of the gas pipeline in the tunnel
    using the floating method and subsequent backfill grouting of the tunnel
  • extensive soil investigation

Construction method

  • TBM tunnelling using a Hydroshield (slurry shield)
  • Shield diameter: 3.6 m
  • Steel fibre reinforced segmental lining
  • Wall thickness 25 cm

Geology

  • Potklei (local type of clay)
  • Sands
  • Clays

 

 

General data

Project

Ems-Dollard Crossing between Germany and the Netherlands
tunnel for a gas pipeline

Client

Nederlandse Gasunie

Contractor

Wayss & Freytag Ingenieurbau AG
in a joint venture

Construction period

June 2008 to September 2010

Construction costs

€ 45.7 million
Utilisation
Media / Supply
Type
Cable tunnel
Length
4,050 m
Construction Method
TBM tunneling using a Hydroshield (slurry method)
Related Projects

Related Projects

Seepage Water Tunnel „Sylvensteinspeicher“
Seepage Water Tunnel „Sylvensteinspeicher“
Germany

Rehabilitation of the water reservoir ensures the flood protection in the Isar valley. The construction section comprises the construction of the seepage water tunnel as well as the access structures at both ends of the tunnel.

Read more
Hubertus Tunnel
Hubertus Tunnel
Netherlands

A first in the Netherlands - TBM drive in the city centre: Hubertus tunnel, the longest inner-city road tunnel in the Netherlands, completes the Northern “Randweg” of The Hague.

Read more
Weser crossing
Weser crossing
Germany

1 four-lane motorway tunnel, total tunnel length 1,100 m, length of total section on our behalf approx. 4,800m.

Read more