Technical specifications

Scope of work

  • Tunnel for a gas pipeline
    Length: 4,900 m
    Internal diameter: 3.50 m
  • Installation of the gas pipeline (diameter 50 cm)
  • 2 water pipelines (diameter 25 cm) and several control cables
    into the tunnel using the floating method
  • Complete grout backfilling of the tunnel
    after installation of the pipelines and cables

Construction method

  • TBM tunnelling using a Hydroshield (slurry shield),
    shield diameter: 4.24 m
  • Steel fibre reinforced segmental lining
    Wall thickness 25 cm

Geology 

  • Quaternary sands
  • Gravels
  • Gneiss

 

 

General data

Project

Corrib Pipeline Tunnel,
utility tunnel for a gas pipeline

Client

Shell E&P Ireland Limited, Dublin, Ireland

Contractor

Wayss & Freytag Ingenieurbau AG
in a joint venture

Construction period

November 2010 to February 2015

Construction costs

€ 125 million
Utilisation
Media / Supply
Type
Cable tunnel
Length
4,900 m
Construction Method
TBM tunneling using a Hydroshield (slurry method)

Wayss & Freytag Ingenieurbau, Area Tunnelling, in a joint venture, built a 4,900 m long tunnel for a gas pipeline under Sruwaddacon Bay for the client Shell E&P Ireland Limited. The tunnel has a light diameter of 3.50 m. Not only the gas pipeline was installed in this tunnel, but also control cables, a water pipe and an empty pipe in which a further gas pipeline might be installed. Afterwards the tunnel was backfilled.

The tunnel boring machine for the Corrib Pipeline tunnel project was named „Fionnuala“. The launching ceremony took place at the Corrib Onshore Pipeline project site in Aughoose, County Mayo, Ireland. The hydroshield TBM „Fionnuala“, with a shield diameter of 4.24 m, reached its target at the target shaft spot on May 19 at 5 pm. The tunnel drive started in the beginning of 2013 at the start shaft in Aughoose and while crossing the 4.9 km long section under Sruwaddacon Bay both the TBM and the tunnel team had to meet all kinds of challenges. On the first approx. one kilometre long section the geology proved to be very abrasive, which required extensive tool replacement under compressed air. This was followed by a loose soil section in which Fionnuala picked up speed and finally successfully coped with the last 500 m, again rock. On May 21, the 4062nd and at the same time last ring was installed.

During the 2015 Tunnelling Awards, the International Tunnelling Association (ITA), with its head office in Geneva, awarded the Corrib Tunnel project the prize for best environmental initiative of the year. Originally, it was planned to run the gas pipeline above ground along the edge of the bay. However, to minimize the impact both on the environment and on the inhabitants, Shell decided in favour of the tunnel solution. Even during site installation, greatest possible attention was paid to the protection of the environment; e.g. with regard to limited heights, colours chosen and especially measures for the protection of birds.

Related Projects

Related Projects

North-South-Link Antwerp (ASDAM)
North-South-Link Antwerp (ASDAM)
Belgium

The North-South link Antwerp is part of the Brussels-Amsterdam high-speed line. The project comprises the reconstruction of the existing accesses, the construction of a passage under the main station as well as the construction of two tunnel sections from „Astridplatz“ to „Damplatz“.

Read more
New Coal-Fired Power Plant in Wilhelmshaven
New Coal-Fired Power Plant in Wilhelmshaven
Germany

High quality and in time: four cooling water pipelines in pipe jacking drive for a new coal-fired power plant in Wilhelmshaven.

Read more
Uetliberg Tunnel
Uetliberg Tunnel
Switzerland

Greatly varying geology required different driving methods during the construction of the Uetliberg Tunnel in Switzerland. The 4.4 km long road tunnel connects the Birmensdorf bypass with the existing national road Zurich-Chur.

Read more