Technical specifications

Project description

  • two-lane road tunnel, L = 1,100 m, A = 85 m²
  • 1 breakdown bay
  • 2 escape tunnels L= 600 m, A = 25 m²

Construction method
Combination of tunnel excavator and drill and blast

Geology
Phyllite

General data

Project
Völkermarkt Bypass, two-lane road tunnel

Client
Land Kärnten, Abteilung 17 - Brücken und Tunnels
[State of Carinthia, Division 17 - Bridges and Tunnels]

Contractor
Wayss & Freytag Ingenieurbau AG
in a joint venture

Construction period
2007 to 2009

Construction costs
€ 23 million

Utilisation
Infrastructure
Type
Road Tunnel, double-track
Length
1,100 m
Construction Method
Drill and blast method in combination with tunnel excavator
Related Projects
Roppen Tunnel JV
Roppen Tunnel JV
Austria

The Roppen tunnel between Innsbruck and Landeck in Austria was made safer by the construction of the second tube. The 5,069 meter long tunnel was driven conventionally.

Read more
Grouft Tunnel
Grouft Tunnel
Luxembourg

A double-lane motorway tunnel with a length of approx. 3 km forms part of the new motorway section of ‚Route du Nord' in the biggest infrastructure project in Luxembourg. The two tubes were carried out with an incline of nearly 5%.

Read more
Rennsteig Tunnel
Rennsteig Tunnel
Germany

The longest motorway tunnel in Germany is the centrepiece of the new A 71 federal motorway from Erfurt to Schweinfurt.

Read more