Technical specifications

Project description

  • Two-lane road tunnel,
    Length 460 m; A= 95 - 120m²
  • Escape and safety tunnels,
    Length = 328 m, A = 13.5 – 18.3 m²

Construction method
Drill and blast

Geology
Upper shell limestone

General data

Project
Darmsheim Northern Bypass
L1182 Darmsheim Tunnel

Client
Federal Land of Baden-Württemberg
represented by RP Stuttgart

Contractor 
Wayss & Freytag Ingenieurbau AG

Construction period
2015 to 2017

Construction costs
€ 13.5 million

Usage
Infrastructure
Type
Road tunnel, two-lane
Length
Length: 460 m
Construction Method
Drill and blast

Related Projects
Tunnel Vötting
Tunnel Vötting
Germany

95 m preliminary cut, preliminary cut approx. 35,000 m³ 30 m north portal structure 462 m tunnel constructed by the mining method: Top heading and bench/invert heading in Tertiary hilly terrain

Read more
Bad Cannstatt Tunnel
Bad Cannstatt Tunnel
Germany

6 km railway tunnel from Stuttgart central railway station to Bad Cannstatt as part of the large-scale project „Stuttgart 21“.

Read more
Georgsberg Tunnel,
Georgsberg Tunnel,
Germany

Foot and cycle path tunnel, length 114.77 m, max. clear width 6.45 m, clear height approx. 4.22 m.

Read more