Technical specifications

Length / Width / Depth substructure

19.20 m / 14.10 m / 11.10 m


Length / Width / Depth superstructure

20.85 m / 14.10 m / up to 8.00 m

Length / Width / Depth Superstructure E-rooms

3.10 m / 14.70 m / 3.80 m

Structural concrete

1,800 m³


Reinforcement

195 t

Underwater concrete

300 m³

Soil excavation, total

4,500 m³

Sheet pile area

1,550 m²

General data

Project

Construction of the new Berlin XII Sewerage Pumping Station,
Rudolfstraße 15, 10245 Berlin


Client

Berliner Wasserbetriebe (Berlin Water Authority)
Neue Jüdenstraße 1, 10846 Berlin

Contractor

Wayss & Freytag Ingenieurbau AG
Bereich Nord, Niederlassung Berlin (Area North, Berlin Branch)
Straße der Jugend 58, 14974 Ludwigsfelde

Project planning

A-plan Martin Baisenwenger
Belziger Straße 25, 10823 Berlin

Structural engineering

KLW Ingenieure GmbH
Hauptstraße 65, 12159 Berlin
p2m berlin GmbH
Fasanenstraße 7-8, 10623 Berlin

Construction time

February 2011 to December 2013

Contract value

2.2 m €

 

Related Projects

Related Projects

Refurbishment Kreuzbauten in Bonn
Refurbishment Kreuzbauten in Bonn
Germany

A listed property of the German Federation was rehabilitated without interrupting operations.

Read more
Sewerage Pumping Station Berlin-Adlershof
Sewerage Pumping Station Berlin-Adlershof
Germany

Alternative proposal for a new sewerage pumping station led to a reduction in construction period and cost as well as an increase in work safety. It replaces old pumping stations which had fallen into disrepair at the Berlin Adlershof science and research centre.

Read more
Extension Building 66, Daimler AG, Bremen
Extension Building 66, Daimler AG, Bremen
Germany

The simultaneous execution of various construction works in combination with perfect coordination and effective interaction led to a time saving of 1.5 months and accident-free construction. That convinced the client.

Read more