Technical specifications

Scope of work

  • 2 double-lane tunnels
    each 1,490 m long
    internal diameter: 9.40 m
  • 2 ramp structures
  • 5 cross-passages

Construction method

  • TBM tunnelling using a Mixshield (slurry shield)
  • External diameter of TBM: 10.50 m
  • Reinforced concrete segmental lining

Geology
Silty fine sands to medium dense beach sands

General data

Project
Hubertus Tunnel
Road tunnel

Client
Gemeente Den Haag [Municipality of The Hague]
the Netherlands

Contractor
Wayss & Freytag Ingenieurbau AG
in a joint venture

Construction period
September 2004 to September 2008

Construction costs
€ 109 million

Utilisation
Infrastruktur
Type
Road Tunnel
Length
2 * 1,490 m
Construction Method
TBM tunneling using a Mixshield
Related Projects
Oenzberg Tunnel
Oenzberg Tunnel
Switzerland

The 3.1 km long Oenzberg tunnel is part of the new Mattstetten-Rothrist railway line in Switzerland. This railway line improves the connection between Bern and Olten.

Read more
Uetliberg Tunnel
Uetliberg Tunnel
Switzerland

Greatly varying geology required different driving methods during the construction of the Uetliberg Tunnel in Switzerland. The 4.4 km long road tunnel connects the Birmensdorf bypass with the existing national road Zurich-Chur.

Read more
New Culvert Brunsbüttel Lock
New Culvert Brunsbüttel Lock
Germany

Increase in the shipping capacity of the Kiel Canal (Nord-Ostsee-Kanal): Pipe jacking for a pipeline tunnel 35 m below ground during ongoing lock operation.

Read more

Cookies Policy

Our website uses cookies to improve your experience. Certain cookies can contain personal information. We deactivate Cookies, unless you allow Cooky usage.
Additional information

Allow Cookies
Do not allow cookies
Cookies Settings