Technical specifications

Scope of work

  • 2 parallel railway tunnels
  • length: 5.3 km each
  • internal diameter: 7.15 m
  • 7 cross-passages
  • 1 ventilation shaft

Construction method

  • TBM tunnelling using 2 EPB shields
  • shield diameter: 8.15 m
  • steel fibre reinforced segmental lining
  • both tunnels driven simultaneously from a retained cut structure

Geology

  • Sand
  • London Clay
  • Silt
  • Gravel

General data

Project
Channel Tunnel Rail Link
Contract C250
single-track railway tunnel

Client
Union Railways (North) Ltd.,
London, UK

Contractor
Wayss & Freytag Ingenieurbau AG
in a joint venture

Construction period
February 2001 to September 2004

Construction costs
€ 217 m

Utilisation
Infrastructure
Type
Railway tunnel, single-track
Length
2 * 5.3 km
Construction Method
TBM tunneling using a EPB shield
Related Projects
Emscher Sewerage Tunnel
Emscher Sewerage Tunnel
Germany

47 km sewerage tunnel across the Ruhr area

Read more
SMART Tunnel
SMART Tunnel
Malaysia

A clever solution: What is normally a road tunnel turns into a storm water relief tunnel during floods. The storm water management and road tunnel in Malaysia is the answer to two challenges.

Read more
Uetliberg Tunnel
Uetliberg Tunnel
Switzerland

Greatly varying geology required different driving methods during the construction of the Uetliberg Tunnel in Switzerland. The 4.4 km long road tunnel connects the Birmensdorf bypass with the existing national road Zurich-Chur.

Read more

Cookies Policy

Our website uses cookies to improve your experience. Certain cookies can contain personal information. We deactivate Cookies, unless you allow Cooky usage.
Additional information

Allow Cookies
Do not allow cookies
Cookies Settings