Technical specifications

Scope of work
Construction of two pilot tunnels
in the course of the construction of Leipzig City Tunnel,
Section C

Length

  • 110 m and 145 m
  • Internal diameter: 2.40 m

Construction method

Pipe jacking with a slurry-supported tunnel face

  • AVN 2000 tunnelling machine
  • External diameter: 2,400 mm
  • Enlarged to 3,000 mm

Wall thickness of jacking pipes 

  • 30 cm, standard length: 3 m;
  • Max. settlement 3 mm

Geology

  • Sand
  • Gravel

General data

Project 
Pipe jacking under Leipzig Main Station

Client 
City Tunnel Leipzig Joint Venture consisting of

  • Wayss & Freytag Ingenieurbau AG
  • and Strabag AG

Contractor 
Wayss & Freytag Ingenieurbau AG
as technical leader of a joint venture

Construction period
October 2006 to July 2007

Construction costs
€ 2.8 million

Utilisation
Infrastructure
Type
Pilot tunnel
Length
110 and 145 m
Construction Method
Pipe Jacking
Related Projects
SMART Tunnel
SMART Tunnel
Malaysia

A clever solution: What is normally a road tunnel turns into a storm water relief tunnel during floods. The storm water management and road tunnel in Malaysia is the answer to two challenges.

Read more
Munich Underground, Line 3 North, Lot 2
Munich Underground, Line 3 North, Lot 2
Germany

The new underground line provides a connection between the Moosach district and the „Olympia” shopping centre which was also built by W&F Ingenieurbau.

Read more
Emscher Sewerage Tunnel
Emscher Sewerage Tunnel
Germany

47 km sewerage tunnel across the Ruhr area

Read more

Cookies Policy

Our website uses cookies to improve your experience. Certain cookies can contain personal information. We deactivate Cookies, unless you allow Cooky usage.
Additional information

Allow Cookies
Do not allow cookies
Cookies Settings