Technical specifications

Construction of a services tunnel (called “Mitteldüker”) under the existing double locks at the western end of the Kiel Canal without disrupting lock operations

  • Length: approx. 450 m
  • Clear internal diameter: 2.20 m
  • Tunnel invert approx. 35 m below ground level

Construction method

  • Pipe jacking using an AVN 2000 machine
  • Construction of shafts using the diaphragm wall method

Geology

  • Gravelly sand with stones

General data

Project
New central services tunnel for Brunsbüttel lock
tunnel for service lines

Client
Wasser- und Schifffahrtsamt Brunsbüttel [Water and Shipping Authority]

Contractor
Wayss & Freytag Ingenieurbau AG

Construction period
March 2009 to September 2011

Construction costs
€ 22 million

Utilisation
Logistics
Type
Utility tunnel
Length
450 m
Construction Method
Pipe Jacking

Central Service Tunnel for the Large Lock of the Kiel Canal Locks, Brunsbüttel, Germany

The Kiel Canal is the most heavily frequented artificial waterway in the world. Up to 45,000 vessels pass through this canal every year, most of which go through the two lock chambers of the double locks at the western end of the Kiel Canal, which were opened to traffic in 1895 and 1914.

Due to a substantial increase in traffic and because the lock chambers were in need of repair, the construction of an additional - the fifth - lock chamber became necessary.

In preparation for the construction of this lock chamber a new service tunnel for cables and pipelines was built underneath the locks without disrupting the vessel traffic. The service tunnel with an internal diameter of 2.20 m and a length of approx. 450 m was constructed using the pipe jacking technique. A specially designed AVN 2000D machine was used to drive the tunnel. The tunnel invert is situated approx. 35 m below ground surface level.

The project also comprises the construction of 5 shafts with an average depth of 35 m, including the launching and reception shaft for the AVN machine. Most of the shafts were built using the diaphragm wall method.

Related Projects
Emscher Sewerage Tunnel
Emscher Sewerage Tunnel
Germany

47 km sewerage tunnel across the Ruhr area

Read more
Weinberg Tunnel, Lots 3.1 and 3.2
Weinberg Tunnel, Lots 3.1 and 3.2
Switzerland

The Zurich main station - Altstetten - Oerlikon cross-city line forms the central part of the West- East-axis of the Swiss railway lines. The Weinberg tunnel is the centrepiece of the cross-city line and connects the new through station “Löwenstraße” in Zurich with Oerlikon station.

Read more
Metro Singapore, North-East Line, Lot
Metro Singapore, North-East Line, Lot
Singapore

2.5 km long underground railway line in a double-tube underground track system for the North-East-Line (NEL) in Singapore with two stations, two underground passages and a flyover.

Read more

Cookies Policy

Our website uses cookies to improve your experience. Certain cookies can contain personal information. We deactivate Cookies, unless you allow Cooky usage.
Additional information

Allow Cookies
Do not allow cookies
Cookies Settings