Technical specifications

Scope of work:
Length: 3.6 km, excavated area: 40 m²

Construction method:
Excavation using a roadheader with pneumatic-tired material transport; single-pass lining, with anchored shotcrete, partly with arches

Geology:
Molasse, partly eroded

General data

Project: Tridel Tunnel in Lausanne, Switzerland, single-track railway tunnel
Client: Tridel SA, Lausanne, Switzerland
Contractor: Wayss & Freytag Ingenieurbau AG in a joint venture
Construction period: 2004 to 2006
Construction costs: € 35 million

Utilisation
Infrastructure
Type
Railway tunnel, single-track
Length
3.6 km
Construction Method
Excavation using a roadheader with pneumatic-tired material transport
Related Projects
Stafelter Tunnel
Stafelter Tunnel
Luxembourg

The approx. 2 km long „Stafelter Berg“ Tunnel, north of Luxembourg city is part of the new motorway section of ‚Route du Nord‘ and consists of two double-lane tubes. The tunnel drive was carried out conventionally and with the drill and blast method.

Read more
Henndorf Bypass
Henndorf Bypass
Austria

The Henndorf bypass lead to a noticeable relief of traffic congestion. Centrepiece of the bypass is the double lane 2,150 meters long road tunnel, which is now used by approx. 20,000 vehicles per day.

Read more
Light Railway Dortmund “Ostentor”
Light Railway Dortmund “Ostentor”
Germany

New U-railway line in the center of Dortmund will replace the existing overground running tram.

Read more

Cookies Policy

Our website uses cookies to improve your experience. Certain cookies can contain personal information. We deactivate Cookies, unless you allow Cooky usage.
Additional information

Allow Cookies
Do not allow cookies
Cookies Settings