Technical specifications

Scope of work

  • Double-track mined tunnel
  • Length: 380 m, excavated crosssection: 90 m²;
  • 852 m constructed using the cut and cover method

Construction method

  • Sprayed concrete lining (SCL) method with tunnel excavator
  • Tunnelling under a high rise building
    protected by a pipe umbrella support system,
    under a four-lane federal road and an industrial building with a shallow overburden

Geology
Sandstone of varying strength

General data

Project
U6 metro link to Fasanenhof
double-track tunnel

Client
Stuttgarter Straßenbahnen AG

Contractor
Wayss & Freytag Ingenieurbau AG
as technical leader of a joint venture

Construction period
2007 to 2010

Construction costs
€ 30 million

Utilisation
Infrastructure
Type
Metro tunnel, double-track
Length
2 * 380 m
Construction Method
Sprayed concrete lining (SCL) method with tunnel excavator
Related Projects
Koralm Tunnel KAT 1
Koralm Tunnel KAT 1
Austria

The centrepiece of the 125 km long, double-track high-speed line between Graz and Klagenfurt is simultaneously the key project for the Baltic-Adriatic-Corridor. The Koralm Tunnel improves the traffic link between Graz and Klagenfurt.

Read more
Vienna Underground Line – U2/2
Vienna Underground Line – U2/2 "Taborstraße"
Austria

During the construction of the Vienna underground line 2 extensive dewatering works with approx. 270 wells and approx. six million pumping hours were required. An electronic monitoring and control system made the measure safe.

Read more
Roppen Tunnel JV
Roppen Tunnel JV
Austria

The Roppen tunnel between Innsbruck and Landeck in Austria was made safer by the construction of the second tube. The 5,069 meter long tunnel was driven conventionally.

Read more