Technical specifications

Project description

  • Two-lane road tunnel,
    Length 460 m; A= 95 - 120m²
  • Escape and safety tunnels,
    Length = 328 m, A = 13.5 – 18.3 m²

Construction method
Drill and blast

Geology
Upper shell limestone

General data

Project
Darmsheim Northern Bypass
L1182 Darmsheim Tunnel

Client
Federal Land of Baden-Württemberg
represented by RP Stuttgart

Contractor 
Wayss & Freytag Ingenieurbau AG

Construction period
2015 to 2017

Construction costs
€ 13.5 million

Usage
Infrastructure
Type
Road tunnel, two-lane
Length
Length: 460 m
Construction Method
Drill and blast

Related Projects
Bad Cannstatt Tunnel
Bad Cannstatt Tunnel
Germany

6 km railway tunnel from Stuttgart central railway station to Bad Cannstatt as part of the large-scale project „Stuttgart 21“.

Read more
Light Railway Dortmund “Ostentor”
Light Railway Dortmund “Ostentor”
Germany

New U-railway line in the center of Dortmund will replace the existing overground running tram.

Read more
Tridel Tunnel
Tridel Tunnel
Switzerland

Due to an advantageous layout of tunnel portal and tunnel excavator is was possible to do without shunting bays and laborious shunting during the construction of the single-track railway tunnel.

Read more

Cookies Policy

Our website uses cookies to improve your experience. Certain cookies can contain personal information. We deactivate Cookies, unless you allow Cooky usage.
Additional information

Allow Cookies
Do not allow cookies
Cookies Settings